New Mississippi River bridge at Lansing to open around 12:30 p.m. Friday

Oct 31, 2026, 9:06 PM•Dubuque, Iowa
New Mississippi River bridge at Lansing to open around 12:30 p.m. Friday
LOCAL NEWS WIRE • October 31, 2026

Ferry ends Nov. 6 as the $140 million Iowa 9/WIS 82 crossing opens months early

KEY FACTS & RECORD HIGHLIGHTS
  • Traffic opens around 12:30 p.m. Friday, Nov. 6, per the Iowa DOT (reported by KCRG Oct. 30).
  • The car ferry runs Nov. 6, then is discontinued.
  • Carries Iowa 9 / WIS 82 between Lansing, Iowa, and rural Crawford County, Wisconsin.
  • Replaces the Black Hawk Bridge (built 1931; closed Oct. 2025; imploded Dec. 2025).
  • $140 million project; 80 percent federal funding.
  • 1,724 feet; concrete deck; mimics the old bridge's look; 40-foot roadway with eight-foot shoulders.
  • Months ahead of the original spring 2027 timeline; contractor Kraemer North America.
  • Free car ferry averaged about 555 vehicles a day in summer 2026; carried nearly 131,000 vehicles in total.
  • The only Mississippi crossing for roughly 60 miles, between La Crosse and Prairie du Chien.
  • Remaining work through spring 2027 (ferry landing restoration, old pier removal); no full closures expected.
Traffic will be open on the new Mississippi River bridge at Lansing starting around 12:30 p.m. Friday, Nov. 6, the Iowa Department of Transportation says, and the car ferry will run its last day the same day. The $140 million concrete-deck bridge carries Iowa 9 and Wisconsin 82 between Lansing, Iowa, and rural Crawford County, Wisconsin, replacing the nearly century-old Black Hawk Bridge, which closed in October 2025 and was imploded that December. The new 1,724-foot span mimics the old bridge's look with wider lanes and eight-foot shoulders. The opening is months ahead of the original spring 2027 timeline, credited to contractor Kraemer North America and favorable weather and river conditions. During the closure, the free car ferry averaged about 555 vehicles a day in summer 2026. The bridge is the only Mississippi crossing for roughly 60 miles between La Crosse and Prairie du Chien. Work continues through spring 2027, including ferry-landing restoration and removal of the old bridge's piers, with no full closures expected.