County Road Update: Old Highway Rd Culverts and Paving Project Progress Report

**DUBUQUE COUNTY, IA — The Dubuque County Engineering Department has provided an update on the construction work taking place on Old Highway Rd, connecting Peosta and Farley, which focuses on the replacement of culverts and resurfacing of the roadway. This project commenced on Monday, June 9, 2025, at 7:00 AM, affecting an 8.03-mile section of the route.**

**Initial Phase and Current Status**

**The construction initially required a complete closure of Old Highway Rd between Hartbecke Rd and Fishpond Rd, with travel restrictions during daylight hours to facilitate the ongoing work. As of Wednesday, June 18, 2025, the project has advanced into Phase 2, concentrating on the culvert replacement between Peosta and Farley. During this phase, access will be limited to one lane, with traffic directed by flaggers, expected to last for 2-3 weeks, weather allowing. Motorists should be prepared for delays and adjust their travel plans accordingly.**

**Upcoming Phase 3**

**After the conclusion of Phase 2, Phase 3 will begin, which will involve road resurfacing along the same corridor from Peosta to Farley. This stage will implement a pilot car and flaggers to manage traffic safely and effectively. The specific starting date for Phase 3 will be communicated as the completion of Phase 2 approaches.**

**Travel Advisory**

**Residents and commuters are advised to proceed with caution, lower speeds, and adhere to all posted signage within the construction zone. Although the roadway remains open, significant limitations are in place, and alternate routes are encouraged where feasible. Updates will be provided as the project advances, with an emphasis on safety for both workers and drivers.**

**For up-to-date information, residents are encouraged to stay informed through local announcements from the Dubuque County Engineering Department.**