Here is the updated list of streets in Dubuque set for repaving this June, as part of the City’s annual asphalt overlay program. Residents should anticipate minor traffic disruptions lasting no more than one week during these operations.
The complete schedule can be found on the City website: http://www.cityofdubuque.org/asphaltoverlay
Phase Two: June
- Kehl Ct.
- Tomahawk Dr.
- Laurel St. (from S. Grandview Ave. to 815 Laurel St.)
- Cannon St.
- Mount Carmel Rd.
- Arrowhead Dr.
- Wallis Pl.
- Indian Ridge
Phase Three: June-July
- N. Grandview Ave. (from Delhi St. to Loras Blvd.)
- N. Grandview Ave. (from Atlantic St. to Clarke Dr.)
- N. Grandview Ave. (from Clarke Dr. to Kaufmann Ave.)
- Rosedale Ave. (from N. Grandview Ave. to Asbury Rd.)
- St. Ambrose St. (from Clarke Dr. to Asbury Rd.)
Phase Four: July
- Cornell St. (from Loras Blvd. to W. 16th St.)
- Montrose Ter. (from Loras Blvd. to W. 16th St.)
- Fairview Pl. (from W. 16th St. to W. 15th St.)
- W. 15th St. (from Fairview Pl. to Cornell St.)
- W. 16th St. (from Montrose Ter. to dead end)
Phase Five: August-September
- Southgate Dr.
- Jenni St.
- Theisen St.
- Stetmore St.
- St. Joseph St. (from Stetmore St. to S. Algona St.)
- Cardiff St. (from W. 3rd St. to Mazzuchelli St.)
- Mazzuchelli St. (from Cardiff St. to James St.)
- Langworthy St. (from James St. to Hill St.)
- James St. (from Langworthy St. to W. 3rd St.)
- Wooten St. (from Hill St. to Medical Associates entrance)
- Clara Ct.
Phase Six: August-September
- Asbury Rd. (from John F. Kennedy Rd. to Carter Rd.)
- Woodlawn St.
- Chippewa Dr.
- Karen St. (from Evergreen Dr. to Carter Rd.)
- Lindale St. (from Evergreen Dr. to Carter Rd.)
- Kevindale St. (from Karen St. to Lindale St.)
Phase Seven: September
- S. Grandview Ave. (from U.S. 61/151 overpass to Carmel Dr.)
- Carmel Dr. (from S. Grandview Ave. to 1025 Carmel Dr.)
- Julien Dubuque Dr. (north from S. Grandview Ave. to dead end)
- Julien Dubuque Dr. (from S. Grandview Ave. to Inland Ln.)
- Twin Valley Dr. (from Rockdale Rd. to U.S. 61/151)
- Southpark Ct.
- Pinard St. (from E. 24th St. to dead end)
The project timeline is accessible online at www.cityofdubuque.org/asphaltoverlay and will be updated as new information becomes available.